Reducing conservatism in life assessment approaches : industrial steam turbine blade to disc interfaces and the shot peening process
Damage tolerant life assessment and the resulting component repair and replacement scheduling is crucial to the continued operation of UK power plant. Typically a major outage on a conventional power station takes 8 -12 weeks; there is a drive to minimise the scope of remedial works undertaken allow...
Main Author: | |
---|---|
Other Authors: | |
Published: |
University of Southampton
2013
|
Subjects: | |
Online Access: | https://ethos.bl.uk/OrderDetails.do?uin=uk.bl.ethos.581548 |