Critical Failure Factors for Public-Private Partnerships Projects in Taiwan.
碩士 === 國立臺灣大學 === 土木工程學研究所 === 94 === Based on the awareded PPIP(Private Participation in Infrastructure Projects)cases until the first season of 2006 from Public Construction Commission, 78 projects(25.08%)were behind schedule and 6 projects(1.93%) were early terminated in 311 projects. In 231 regi...