Aspects of conversion of the Nelson River bipole 2 HVDC converters from 12-pulse to 6-pulse operation
In the early months of 1979, Manitoba Hydro was confronted with a serious problem involving the converter transformers for the bipole 2 operation of the Nelson River HVDC transmission system. The transformer problem left the negative pole of bipole 2, pole 3, without a converter transformer at...
Main Author: | |
---|---|
Published: |
2012
|
Online Access: | http://hdl.handle.net/1993/6629 |