An alternative technique to the demolition of a prestressed concrete box-girder bridge: A case study
This is a case study in which the partial collapse of a prestressed concrete box-girder bridge in Brazil happened only nine days after removing the supporting scaffolding. It is believed that the actual reinforcement longitudinal steel bars in the pile caps were underestimated. Although only part of...