Scheduling construction projects with resources accessibility limited and changeable in time

This paper aims at solving the problem of minimising the construction project duration in deterministic conditions when the accessibility of renewable resources is limited and changeable in time (workforce, machines and equipment). Particular construction processes (with various levels of complexit...

Full description

Bibliographic Details
Main Authors: Piotr Jaśkowski, Anna Sobotka
Format: Article
Language:English
Published: Vilnius Gediminas Technical University 2004-12-01
Series:Journal of Civil Engineering and Management