Scheduling of Job Resources in Multiunit Projects with the Use of Time I Cost Criteria
This paper presents a model of scheduling of multiunit construction project based on an NP-hard permutation flow shop problem, in which the considered criterion is the sum of the costs of the works’ execution of the project considering the time of the project as a constraint. It is also assumed that...