A Modified PSO Algorithm for Minimizing the Total Costs of Resources in MRCPSP

We introduce a multimode resource-constrained project scheduling problem with finish-to-start precedence relations among project activities, considering renewable and nonrenewable resource costs. We assume that renewable resources are rented and are not available in all periods of time of the proje...