The development of a conceptual framework for a district 4-Year Pavement Management Plan

The Texas Department of Transportation (TxDOT) is concerned about the widening gap between preservation needs and available funding. Funding levels are not adequate to meet the preservation needs of the roadway network; therefore projects listed in the 4-Year Pavement Management Plan must be ranked...

Full description

Bibliographic Details
Main Author: Hwang, Jea Won
Format: Others
Language:English
Published: 2011
Subjects:
Online Access:http://hdl.handle.net/2152/ETD-UT-2011-08-4269
id ndltd-UTEXAS-oai-repositories.lib.utexas.edu-2152-ETD-UT-2011-08-4269
record_format oai_dc
spelling ndltd-UTEXAS-oai-repositories.lib.utexas.edu-2152-ETD-UT-2011-08-42692015-09-20T17:03:24ZThe development of a conceptual framework for a district 4-Year Pavement Management PlanHwang, Jea Won4-Year Pavement Management PlanPrioritizationRankingPavement managementThe Texas Department of Transportation (TxDOT) is concerned about the widening gap between preservation needs and available funding. Funding levels are not adequate to meet the preservation needs of the roadway network; therefore projects listed in the 4-Year Pavement Management Plan must be ranked to determine which projects should be funded now and which can be postponed until a later year. Currently, each district uses locally developed methods to rank and prioritize projects. These ranking methods have relied on less formal qualitative assessments based on engineers’ subjective judgment. It is important for TxDOT to have a rational 4-Year Pavement Management Plan. The objective of this study is to develop a conceptual framework that describes the development of the 4-Year Pavement Management Plan and a proposed ranking process. It can be largely divided into three steps; (1) Network-Level preliminary project screening process, (2) Project-Level project ranking process, and (3) Economic Analysis. A rational pavement management procedure and a project ranking method that are accepted by districts and the TxDOT administration will maximize efficiency in budget allocations and help improve pavement condition. As a part of this study, based on the data provided by the Austin District Pavement Engineer, the Network-Level Project Screening (NLPS) tool, including the candidate project selection algorithm and the preliminary project screening matrix, is developed. The NLSP tool has been used by the Austin District Pavement Engineer (DPE) to evaluate the PMIS (Pavement Management Information System) data and to prepare a preliminary list of candidate projects for further evaluation. The automated tool will help TxDOT engineers easily incorporate the developed mathematical algorithm into their daily pavement maintenance management.text2011-09-30T15:12:17Z2011-09-30T15:12:17Z2011-082011-09-30August 20112011-09-30T15:12:31Zthesisapplication/pdfhttp://hdl.handle.net/2152/ETD-UT-2011-08-42692152/ETD-UT-2011-08-4269eng
collection NDLTD
language English
format Others
sources NDLTD
topic 4-Year Pavement Management Plan
Prioritization
Ranking
Pavement management
spellingShingle 4-Year Pavement Management Plan
Prioritization
Ranking
Pavement management
Hwang, Jea Won
The development of a conceptual framework for a district 4-Year Pavement Management Plan
description The Texas Department of Transportation (TxDOT) is concerned about the widening gap between preservation needs and available funding. Funding levels are not adequate to meet the preservation needs of the roadway network; therefore projects listed in the 4-Year Pavement Management Plan must be ranked to determine which projects should be funded now and which can be postponed until a later year. Currently, each district uses locally developed methods to rank and prioritize projects. These ranking methods have relied on less formal qualitative assessments based on engineers’ subjective judgment. It is important for TxDOT to have a rational 4-Year Pavement Management Plan. The objective of this study is to develop a conceptual framework that describes the development of the 4-Year Pavement Management Plan and a proposed ranking process. It can be largely divided into three steps; (1) Network-Level preliminary project screening process, (2) Project-Level project ranking process, and (3) Economic Analysis. A rational pavement management procedure and a project ranking method that are accepted by districts and the TxDOT administration will maximize efficiency in budget allocations and help improve pavement condition. As a part of this study, based on the data provided by the Austin District Pavement Engineer, the Network-Level Project Screening (NLPS) tool, including the candidate project selection algorithm and the preliminary project screening matrix, is developed. The NLSP tool has been used by the Austin District Pavement Engineer (DPE) to evaluate the PMIS (Pavement Management Information System) data and to prepare a preliminary list of candidate projects for further evaluation. The automated tool will help TxDOT engineers easily incorporate the developed mathematical algorithm into their daily pavement maintenance management. === text
author Hwang, Jea Won
author_facet Hwang, Jea Won
author_sort Hwang, Jea Won
title The development of a conceptual framework for a district 4-Year Pavement Management Plan
title_short The development of a conceptual framework for a district 4-Year Pavement Management Plan
title_full The development of a conceptual framework for a district 4-Year Pavement Management Plan
title_fullStr The development of a conceptual framework for a district 4-Year Pavement Management Plan
title_full_unstemmed The development of a conceptual framework for a district 4-Year Pavement Management Plan
title_sort development of a conceptual framework for a district 4-year pavement management plan
publishDate 2011
url http://hdl.handle.net/2152/ETD-UT-2011-08-4269
work_keys_str_mv AT hwangjeawon thedevelopmentofaconceptualframeworkforadistrict4yearpavementmanagementplan
AT hwangjeawon developmentofaconceptualframeworkforadistrict4yearpavementmanagementplan
_version_ 1716822160449732608