Bygg gärna, men inte här! : Ledtider och kostnader i Detaljplaneprocessen

This thesis examines the Swedish detailed planning process from a time and money perspective, and also points out the deficiencies of the process. The detailed planning process currently receives much criticism from both the society and the industry. It is usually considered as a brake in the produc...

Full description

Bibliographic Details
Main Authors: Gälman, Christoffer, Ekelöw, Tobias
Format: Others
Language:Swedish
Published: Uppsala universitet, Byggteknik 2016
Subjects:
Online Access:http://urn.kb.se/resolve?urn=urn:nbn:se:uu:diva-301490
id ndltd-UPSALLA1-oai-DiVA.org-uu-301490
record_format oai_dc
spelling ndltd-UPSALLA1-oai-DiVA.org-uu-3014902016-08-26T05:06:52ZBygg gärna, men inte här! : Ledtider och kostnader i DetaljplaneprocessensweA cost and time analysis in the detailed planning process.Gälman, ChristofferEkelöw, TobiasUppsala universitet, ByggteknikUppsala universitet, Byggteknik2016Samhällsplaneringdetaljplaneprocessenplanprocessenöverklagade detaljplanerledtiderplankostnaderThis thesis examines the Swedish detailed planning process from a time and money perspective, and also points out the deficiencies of the process. The detailed planning process currently receives much criticism from both the society and the industry. It is usually considered as a brake in the production of new housing in Sweden. A few of the municipalities’ administration time in the planning process in Stockholm was compared and analyzed and it was concluded that the average process takes between 30-60 months. However if a zoning plan is appealed the process extends usually between 4 to 12 months. In Stockholm County, a fourth of all the zoning plans are appealed, but only 1.3% of these leads to repealing of the plan. This number questions to some extent the democracy in today’s society, how many of the citizens’ complaints are actually accepted since that number also include complaints from authorities like the county administrative board. To obtain an understanding of the developer’s cost of the planning process a couple of housing projects in the municipality of Stockholm and Solna were examined. The investigation revealed that the cost may vary anywhere between 650,000 up to 6.5 million SEK. The cost of the zoning plan proved to be highly correlated with the time spent. The recommendation from our side is to increase the exchange of information between all parties, including the party concerned, leading to benefits of the process as a whole. Less public opposition leads to a smoother process, while increasing the cooperation between the municipality and the developer do as well. Detta examensarbete undersöker detaljplaneprocessen utifrån ett tids- och kostnadsperspektiv och belyser även processens brister. Detaljplaneprocessen får idag mycket kritik från olika håll och målas upp som en bromskloss i produktionen av nya bostäder i Sverige. Vissa kommuners hanteringstid för detaljplaneprocessen i Stockholms län visade på att den genomsnittliga processen tar mellan 30-60 månader. Överklagas en detaljplan förlängs processen vanligtvis med 4 till 12 månader. I Stockholms län överklagas en fjärdedel av alla detaljplaner, men endast 1,3 % av dessa leder till att detaljplanen upphävs. Utöver det låga antalet som vinner bifall, ifrågasätter siffrorna också i viss mån demokratin i dagens samhälle, hur många av medborgarnas klagomål får bifall, jämtemot hur antalet av myndigheter, såsom Länsstyrelsens klagomål. För att få ett grepp om byggherrens kostnad undersöktes ett par flerbostadsprojekt i Stockholms kommun, med ett par i Solna. Undersökningen visade på att kostnaden kan skilja allt mellan 650 000 upp till 6 500 000 SEK. Kostnaden för detaljplaneprocessen visar sig ha stark korrelation med tiden. Rekommendationerna från vårt håll landar i att ett ökat informationsutbyte mellan alla parter, inklusive sakägare, gagnar processen som helhet. Färre klagomål från allmänheten leder till en smidigare process för både byggherrar och kommunen, samtidigt som ett ökat samarbete också bidrar. Student thesisinfo:eu-repo/semantics/bachelorThesistexthttp://urn.kb.se/resolve?urn=urn:nbn:se:uu:diva-301490application/pdfinfo:eu-repo/semantics/openAccess
collection NDLTD
language Swedish
format Others
sources NDLTD
topic Samhällsplanering
detaljplaneprocessen
planprocessen
överklagade detaljplaner
ledtider
plankostnader
spellingShingle Samhällsplanering
detaljplaneprocessen
planprocessen
överklagade detaljplaner
ledtider
plankostnader
Gälman, Christoffer
Ekelöw, Tobias
Bygg gärna, men inte här! : Ledtider och kostnader i Detaljplaneprocessen
description This thesis examines the Swedish detailed planning process from a time and money perspective, and also points out the deficiencies of the process. The detailed planning process currently receives much criticism from both the society and the industry. It is usually considered as a brake in the production of new housing in Sweden. A few of the municipalities’ administration time in the planning process in Stockholm was compared and analyzed and it was concluded that the average process takes between 30-60 months. However if a zoning plan is appealed the process extends usually between 4 to 12 months. In Stockholm County, a fourth of all the zoning plans are appealed, but only 1.3% of these leads to repealing of the plan. This number questions to some extent the democracy in today’s society, how many of the citizens’ complaints are actually accepted since that number also include complaints from authorities like the county administrative board. To obtain an understanding of the developer’s cost of the planning process a couple of housing projects in the municipality of Stockholm and Solna were examined. The investigation revealed that the cost may vary anywhere between 650,000 up to 6.5 million SEK. The cost of the zoning plan proved to be highly correlated with the time spent. The recommendation from our side is to increase the exchange of information between all parties, including the party concerned, leading to benefits of the process as a whole. Less public opposition leads to a smoother process, while increasing the cooperation between the municipality and the developer do as well. === Detta examensarbete undersöker detaljplaneprocessen utifrån ett tids- och kostnadsperspektiv och belyser även processens brister. Detaljplaneprocessen får idag mycket kritik från olika håll och målas upp som en bromskloss i produktionen av nya bostäder i Sverige. Vissa kommuners hanteringstid för detaljplaneprocessen i Stockholms län visade på att den genomsnittliga processen tar mellan 30-60 månader. Överklagas en detaljplan förlängs processen vanligtvis med 4 till 12 månader. I Stockholms län överklagas en fjärdedel av alla detaljplaner, men endast 1,3 % av dessa leder till att detaljplanen upphävs. Utöver det låga antalet som vinner bifall, ifrågasätter siffrorna också i viss mån demokratin i dagens samhälle, hur många av medborgarnas klagomål får bifall, jämtemot hur antalet av myndigheter, såsom Länsstyrelsens klagomål. För att få ett grepp om byggherrens kostnad undersöktes ett par flerbostadsprojekt i Stockholms kommun, med ett par i Solna. Undersökningen visade på att kostnaden kan skilja allt mellan 650 000 upp till 6 500 000 SEK. Kostnaden för detaljplaneprocessen visar sig ha stark korrelation med tiden. Rekommendationerna från vårt håll landar i att ett ökat informationsutbyte mellan alla parter, inklusive sakägare, gagnar processen som helhet. Färre klagomål från allmänheten leder till en smidigare process för både byggherrar och kommunen, samtidigt som ett ökat samarbete också bidrar.
author Gälman, Christoffer
Ekelöw, Tobias
author_facet Gälman, Christoffer
Ekelöw, Tobias
author_sort Gälman, Christoffer
title Bygg gärna, men inte här! : Ledtider och kostnader i Detaljplaneprocessen
title_short Bygg gärna, men inte här! : Ledtider och kostnader i Detaljplaneprocessen
title_full Bygg gärna, men inte här! : Ledtider och kostnader i Detaljplaneprocessen
title_fullStr Bygg gärna, men inte här! : Ledtider och kostnader i Detaljplaneprocessen
title_full_unstemmed Bygg gärna, men inte här! : Ledtider och kostnader i Detaljplaneprocessen
title_sort bygg gärna, men inte här! : ledtider och kostnader i detaljplaneprocessen
publisher Uppsala universitet, Byggteknik
publishDate 2016
url http://urn.kb.se/resolve?urn=urn:nbn:se:uu:diva-301490
work_keys_str_mv AT galmanchristoffer bygggarnameninteharledtiderochkostnaderidetaljplaneprocessen
AT ekelowtobias bygggarnameninteharledtiderochkostnaderidetaljplaneprocessen
AT galmanchristoffer acostandtimeanalysisinthedetailedplanningprocess
AT ekelowtobias acostandtimeanalysisinthedetailedplanningprocess
_version_ 1718380255531499520