The complex necessity : A qualitative study exploring the current process for grid connection of large-scale onshore wind farms in Sweden

Sweden has a goal of having an electricity production solemnly comprising renewable energy sources by the year 2040. To cater for the fulfillment of this goal, more onshore wind power will be needed in Sweden. The wind farm itself has been studied both in terms of its impacts on societal and environ...

Full description

Bibliographic Details
Main Author: Kuhlefelt, Anna
Format: Others
Language:English
Published: KTH, Hållbar utveckling, miljövetenskap och teknik 2020
Subjects:
DSO
TSO
Online Access:http://urn.kb.se/resolve?urn=urn:nbn:se:kth:diva-281822
id ndltd-UPSALLA1-oai-DiVA.org-kth-281822
record_format oai_dc
collection NDLTD
language English
format Others
sources NDLTD
topic Wind power
network operator
developer
concession
permit
regional
national
transmission
DSO
TSO
Anslutning
elnät
parallella processer
tillståndsprocesser
kapacitet
regionnät
transmissionsnät
vindkraftsprojektör
elnätsägare
Engineering and Technology
Teknik och teknologier
spellingShingle Wind power
network operator
developer
concession
permit
regional
national
transmission
DSO
TSO
Anslutning
elnät
parallella processer
tillståndsprocesser
kapacitet
regionnät
transmissionsnät
vindkraftsprojektör
elnätsägare
Engineering and Technology
Teknik och teknologier
Kuhlefelt, Anna
The complex necessity : A qualitative study exploring the current process for grid connection of large-scale onshore wind farms in Sweden
description Sweden has a goal of having an electricity production solemnly comprising renewable energy sources by the year 2040. To cater for the fulfillment of this goal, more onshore wind power will be needed in Sweden. The wind farm itself has been studied both in terms of its impacts on societal and environmental interests as well as how the Swedish spatial planning system paves the way for more wind power or not. The connection of wind farms to the regional and national transmission grid is far less studied. Therefore, this thesis explores the grid connection process and how it is experienced by the practitioners in terms of wind power developers and network operators. Also, the ways in which the power grid is taken into account when finding a location for a wind farm is studied. This is done by a literature review and a thematic analysis of ten conducted interviews. The grid connection process is presented, along with the four main themes identified by the thematic analysis; Making two long processes parallel, The importance of grid capacity, Dialogue between the developer and the network operator and Proactive consideration of grid connection. The results suggest that the grid connection process, in combination with the wind farm development, is experienced as time-consuming, which gives rise to problems regarding technology development and puts the finalization of the entire project at risk. Consequently, the practitioners want to make the processes more parallel. This is however complicated by the associated risks of not being reassured grid capacity and inflexible permit procedures. Another important result is that the network operators and developers often have different interests to guard, which can complicate the grid connection process further. The available capacity in the grid is crucial when locating a wind farm, but also the economic distance to the point of connection, which in turn depends on several parameters. It is suggested that consideration of the power grid should be more integrated with the spatial planning in Sweden. This can improve the predictability of wind power planning, promote adequate power grid planning and facilitate the Swedish goal of an electricity production only comprised of renewable energy by 2040. === För att genomföra en grön omställning av Europas energisystem väntas mer elproduktion av förnyelsebar energi integreras. Sverige har som mål att ha en elproduktion som enbart består av förnyelsebar energi till år 2040. För att åstadkomma detta mål förväntas andelen vindkraft i landet att öka. Att ansluta till elnätet hör till en av de fundamentala nödvändigheterna för att etablera en vindkraftpark. Trots detta så är planering och utförande av nätanslutning till det svenska elnätet en förbisedd del av processen för att etablera vindkraft i Sverige. Syftet med denna studie är därför att undersöka anslutningsprocessen för landbaserad och storskalig vindkraft och bidra att till ökad kunskap kring hur denna process upplevs av utövarna. Dessutom undersöks det hur vindkraftsprojektörer tar hänsyn till elnätet när de letar områden för vindkraft. Detta görs med en litteraturstudie angående hur anslutningsprocessen går till, följt av en tematisk analys av intervjuer med nätägare och vindkraftsprojektörer. En övergripande bild av anslutningsprocessen och relaterad litteratur presenteras. Fyra huvudteman identifieras från den tematiska analysen; Att göra två långa processer parallella, Signifikansen av nätkapacitet, Dialogen mellan vindkraftsprojektör och nätägare och Proaktiv hänsyn av nätanslutning. Resultaten visar att en stor utmaning med anslutningsprocessen är att den tillsammans med utvecklingen av vindparken upplevs som så pass långdragen i tid, att problem uppstår med teknikutveckling och genomförandet av projektet i sig. Detta bidrar till att vindkraftsprojektörer och nätägare vill försöka göra processerna för utveckling av vindparken och nätanslutningen mer parallella. Att processen för att utveckla vindparken är tidskrävande och osäker bidrar till att den nödvändiga nätkapaciteten inte alltid kan garanteras, vilket försvårar en synkronisering av processerna. Ett ytterligare viktigt resultat är att nätägare och vindkraftsprojektörer ofta har olika intressen under nätanslutningsprocessen, vilket kan komplicera dess förlopp. Var det finns nätkapacitet är en stor faktor vid lokalisering av vindkraft, men även det ekonomiska avståndet till en anslutningspunkt som i sin tur beror på flera parametrar. Elnätsfrågan är komplex både när det gäller lokalisering och anslutning av vindkraft. Men för att skapa goda förutsättningar för mer vindkraft i Sverige, och för uppfyllandet av målet till 2040, bör elnätsfrågan hanteras proaktivt och integreras mer i den fysiska planeringen i Sverige.
author Kuhlefelt, Anna
author_facet Kuhlefelt, Anna
author_sort Kuhlefelt, Anna
title The complex necessity : A qualitative study exploring the current process for grid connection of large-scale onshore wind farms in Sweden
title_short The complex necessity : A qualitative study exploring the current process for grid connection of large-scale onshore wind farms in Sweden
title_full The complex necessity : A qualitative study exploring the current process for grid connection of large-scale onshore wind farms in Sweden
title_fullStr The complex necessity : A qualitative study exploring the current process for grid connection of large-scale onshore wind farms in Sweden
title_full_unstemmed The complex necessity : A qualitative study exploring the current process for grid connection of large-scale onshore wind farms in Sweden
title_sort complex necessity : a qualitative study exploring the current process for grid connection of large-scale onshore wind farms in sweden
publisher KTH, Hållbar utveckling, miljövetenskap och teknik
publishDate 2020
url http://urn.kb.se/resolve?urn=urn:nbn:se:kth:diva-281822
work_keys_str_mv AT kuhlefeltanna thecomplexnecessityaqualitativestudyexploringthecurrentprocessforgridconnectionoflargescaleonshorewindfarmsinsweden
AT kuhlefeltanna complexnecessityaqualitativestudyexploringthecurrentprocessforgridconnectionoflargescaleonshorewindfarmsinsweden
_version_ 1719340443176534016
spelling ndltd-UPSALLA1-oai-DiVA.org-kth-2818222020-09-25T06:02:01ZThe complex necessity : A qualitative study exploring the current process for grid connection of large-scale onshore wind farms in SwedenengKuhlefelt, AnnaKTH, Hållbar utveckling, miljövetenskap och teknik2020Wind powernetwork operatordeveloperconcessionpermitregionalnationaltransmissionDSOTSOAnslutningelnätparallella processertillståndsprocesserkapacitetregionnättransmissionsnätvindkraftsprojektörelnätsägareEngineering and TechnologyTeknik och teknologierSweden has a goal of having an electricity production solemnly comprising renewable energy sources by the year 2040. To cater for the fulfillment of this goal, more onshore wind power will be needed in Sweden. The wind farm itself has been studied both in terms of its impacts on societal and environmental interests as well as how the Swedish spatial planning system paves the way for more wind power or not. The connection of wind farms to the regional and national transmission grid is far less studied. Therefore, this thesis explores the grid connection process and how it is experienced by the practitioners in terms of wind power developers and network operators. Also, the ways in which the power grid is taken into account when finding a location for a wind farm is studied. This is done by a literature review and a thematic analysis of ten conducted interviews. The grid connection process is presented, along with the four main themes identified by the thematic analysis; Making two long processes parallel, The importance of grid capacity, Dialogue between the developer and the network operator and Proactive consideration of grid connection. The results suggest that the grid connection process, in combination with the wind farm development, is experienced as time-consuming, which gives rise to problems regarding technology development and puts the finalization of the entire project at risk. Consequently, the practitioners want to make the processes more parallel. This is however complicated by the associated risks of not being reassured grid capacity and inflexible permit procedures. Another important result is that the network operators and developers often have different interests to guard, which can complicate the grid connection process further. The available capacity in the grid is crucial when locating a wind farm, but also the economic distance to the point of connection, which in turn depends on several parameters. It is suggested that consideration of the power grid should be more integrated with the spatial planning in Sweden. This can improve the predictability of wind power planning, promote adequate power grid planning and facilitate the Swedish goal of an electricity production only comprised of renewable energy by 2040. För att genomföra en grön omställning av Europas energisystem väntas mer elproduktion av förnyelsebar energi integreras. Sverige har som mål att ha en elproduktion som enbart består av förnyelsebar energi till år 2040. För att åstadkomma detta mål förväntas andelen vindkraft i landet att öka. Att ansluta till elnätet hör till en av de fundamentala nödvändigheterna för att etablera en vindkraftpark. Trots detta så är planering och utförande av nätanslutning till det svenska elnätet en förbisedd del av processen för att etablera vindkraft i Sverige. Syftet med denna studie är därför att undersöka anslutningsprocessen för landbaserad och storskalig vindkraft och bidra att till ökad kunskap kring hur denna process upplevs av utövarna. Dessutom undersöks det hur vindkraftsprojektörer tar hänsyn till elnätet när de letar områden för vindkraft. Detta görs med en litteraturstudie angående hur anslutningsprocessen går till, följt av en tematisk analys av intervjuer med nätägare och vindkraftsprojektörer. En övergripande bild av anslutningsprocessen och relaterad litteratur presenteras. Fyra huvudteman identifieras från den tematiska analysen; Att göra två långa processer parallella, Signifikansen av nätkapacitet, Dialogen mellan vindkraftsprojektör och nätägare och Proaktiv hänsyn av nätanslutning. Resultaten visar att en stor utmaning med anslutningsprocessen är att den tillsammans med utvecklingen av vindparken upplevs som så pass långdragen i tid, att problem uppstår med teknikutveckling och genomförandet av projektet i sig. Detta bidrar till att vindkraftsprojektörer och nätägare vill försöka göra processerna för utveckling av vindparken och nätanslutningen mer parallella. Att processen för att utveckla vindparken är tidskrävande och osäker bidrar till att den nödvändiga nätkapaciteten inte alltid kan garanteras, vilket försvårar en synkronisering av processerna. Ett ytterligare viktigt resultat är att nätägare och vindkraftsprojektörer ofta har olika intressen under nätanslutningsprocessen, vilket kan komplicera dess förlopp. Var det finns nätkapacitet är en stor faktor vid lokalisering av vindkraft, men även det ekonomiska avståndet till en anslutningspunkt som i sin tur beror på flera parametrar. Elnätsfrågan är komplex både när det gäller lokalisering och anslutning av vindkraft. Men för att skapa goda förutsättningar för mer vindkraft i Sverige, och för uppfyllandet av målet till 2040, bör elnätsfrågan hanteras proaktivt och integreras mer i den fysiska planeringen i Sverige. Student thesisinfo:eu-repo/semantics/bachelorThesistexthttp://urn.kb.se/resolve?urn=urn:nbn:se:kth:diva-281822TRITA-ABE-MBT ; 20448application/pdfinfo:eu-repo/semantics/openAccess