Concrete Cracks in Composite Bridges : A Case Study of the Bothnia Line Railway Bridge over Ångermanälven

Cracks in the concrete slab of continuous composite bridges are common due to the tensile stresses at the supports. These bridges are allowed to crack as long as the cracking is controlled and not exceeding the design crack width (according to Bro 94 the crack should be injected if they are bigger t...

Full description

Bibliographic Details
Main Authors: Elgazzar, Hesham, Ansnaes, Viktor
Format: Others
Language:English
Published: KTH, Bro- och stålbyggnad 2012
Subjects:
Online Access:http://urn.kb.se/resolve?urn=urn:nbn:se:kth:diva-100831
id ndltd-UPSALLA1-oai-DiVA.org-kth-100831
record_format oai_dc
spelling ndltd-UPSALLA1-oai-DiVA.org-kth-1008312013-01-08T13:52:50ZConcrete Cracks in Composite Bridges : A Case Study of the Bothnia Line Railway Bridge over ÅngermanälvenengElgazzar, HeshamAnsnaes, ViktorKTH, Bro- och stålbyggnadKTH, Bro- och stålbyggnad2012Composite BridgeCracksEdge BeamBothnia LineReinforcement for Crack ControlCracks in the concrete slab of continuous composite bridges are common due to the tensile stresses at the supports. These bridges are allowed to crack as long as the cracking is controlled and not exceeding the design crack width (according to Bro 94 the crack should be injected if they are bigger than 0.2 mm). The Ångermanälven Bridge (railway bridge part of the Bothnia line project) was designed with big edge beams of width 1.2 m, 40 % of the total area of the concrete deck cross-section. During the final inspection cracks larger than the design crack width (0.3 mm according to Bro 94) were observed over the supports.In this thesis the design and the construction procedure of the bridge is studied to clarify the causes of the cracking in the edge beam. The objectives of this thesis were addressed through a literature study of the different types of cracks and the Swedish bridge codes. The expected crack width was calculate according to the same code, using a 2-D FEM model for the moment calculation, and compared with the crack width measured at the bridge.The result of the calculations shows that tensile stress due to ballast and only restraining moment due to shrinkage is not big enough to cause the measured crack width. Shrinkage force and temperature variation effects may have contributed to the concrete cracking in the edge beams. The large cross-section area of the edge beams indicates that it should be designed as part of the slab, taking that into consideration, 1.1 % reinforcement ratio in the edge beams is believed to limit the crack width to the code limits (0.3 mm). Student thesisinfo:eu-repo/semantics/bachelorThesistexthttp://urn.kb.se/resolve?urn=urn:nbn:se:kth:diva-100831Trita-BKN-Examensarbete, 1103-4297 ; 352application/pdfinfo:eu-repo/semantics/openAccess
collection NDLTD
language English
format Others
sources NDLTD
topic Composite Bridge
Cracks
Edge Beam
Bothnia Line
Reinforcement for Crack Control
spellingShingle Composite Bridge
Cracks
Edge Beam
Bothnia Line
Reinforcement for Crack Control
Elgazzar, Hesham
Ansnaes, Viktor
Concrete Cracks in Composite Bridges : A Case Study of the Bothnia Line Railway Bridge over Ångermanälven
description Cracks in the concrete slab of continuous composite bridges are common due to the tensile stresses at the supports. These bridges are allowed to crack as long as the cracking is controlled and not exceeding the design crack width (according to Bro 94 the crack should be injected if they are bigger than 0.2 mm). The Ångermanälven Bridge (railway bridge part of the Bothnia line project) was designed with big edge beams of width 1.2 m, 40 % of the total area of the concrete deck cross-section. During the final inspection cracks larger than the design crack width (0.3 mm according to Bro 94) were observed over the supports.In this thesis the design and the construction procedure of the bridge is studied to clarify the causes of the cracking in the edge beam. The objectives of this thesis were addressed through a literature study of the different types of cracks and the Swedish bridge codes. The expected crack width was calculate according to the same code, using a 2-D FEM model for the moment calculation, and compared with the crack width measured at the bridge.The result of the calculations shows that tensile stress due to ballast and only restraining moment due to shrinkage is not big enough to cause the measured crack width. Shrinkage force and temperature variation effects may have contributed to the concrete cracking in the edge beams. The large cross-section area of the edge beams indicates that it should be designed as part of the slab, taking that into consideration, 1.1 % reinforcement ratio in the edge beams is believed to limit the crack width to the code limits (0.3 mm).
author Elgazzar, Hesham
Ansnaes, Viktor
author_facet Elgazzar, Hesham
Ansnaes, Viktor
author_sort Elgazzar, Hesham
title Concrete Cracks in Composite Bridges : A Case Study of the Bothnia Line Railway Bridge over Ångermanälven
title_short Concrete Cracks in Composite Bridges : A Case Study of the Bothnia Line Railway Bridge over Ångermanälven
title_full Concrete Cracks in Composite Bridges : A Case Study of the Bothnia Line Railway Bridge over Ångermanälven
title_fullStr Concrete Cracks in Composite Bridges : A Case Study of the Bothnia Line Railway Bridge over Ångermanälven
title_full_unstemmed Concrete Cracks in Composite Bridges : A Case Study of the Bothnia Line Railway Bridge over Ångermanälven
title_sort concrete cracks in composite bridges : a case study of the bothnia line railway bridge over ångermanälven
publisher KTH, Bro- och stålbyggnad
publishDate 2012
url http://urn.kb.se/resolve?urn=urn:nbn:se:kth:diva-100831
work_keys_str_mv AT elgazzarhesham concretecracksincompositebridgesacasestudyofthebothnialinerailwaybridgeoverangermanalven
AT ansnaesviktor concretecracksincompositebridgesacasestudyofthebothnialinerailwaybridgeoverangermanalven
_version_ 1716531481725108224