Utvärdering och analys av batchstorlekar, produktsekvenser och omställningstider

Volvo GTO is one of the strongest brands in the truck industry, with a long and proud history of world-leading innovations. The factory in Skövde produces diesel engines of various sizes to Volvo GTO. The project has been carried out on the processing part of grovdel crankshaft. Where the objective...

Full description

Bibliographic Details
Main Authors: Lundberg, Jesper, Mehtonen, Ronja
Format: Others
Language:Swedish
Published: Högskolan i Skövde, Institutionen för ingenjörsvetenskap 2015
Subjects:
Online Access:http://urn.kb.se/resolve?urn=urn:nbn:se:his:diva-11859
id ndltd-UPSALLA1-oai-DiVA.org-his-11859
record_format oai_dc
spelling ndltd-UPSALLA1-oai-DiVA.org-his-118592016-02-04T05:10:22ZUtvärdering och analys av batchstorlekar, produktsekvenser och omställningstidersweEvaluation and analysis of batch sizes, production sequences and setup timesLundberg, JesperMehtonen, RonjaHögskolan i Skövde, Institutionen för ingenjörsvetenskapHögskolan i Skövde, Institutionen för ingenjörsvetenskap2015Processing flowsthroughput per hoursimulation modelchangeoversoptimizationbufferportaloperationinput databuffercycle timesequenceBearbetning flödentakt per timmesimuleringsmodellomställningaroptimeringbuffertportaloperationindatalagercykeltidsekvens.Volvo GTO is one of the strongest brands in the truck industry, with a long and proud history of world-leading innovations. The factory in Skövde produces diesel engines of various sizes to Volvo GTO. The project has been carried out on the processing part of grovdel crankshaft. Where the objective was to construct a simulation model that reflects flows 0, 1 and 2 on the crankshaft grovdel order to produce the best driving style for the size of the batches and sequences, focusing on PIA, between the stock and conversion-up times. A theoretical study intervention gave knowledge to the methodology to ensure that the data is collected and processed correctly. The data were collected in an Excel document, which was integrated with the simulation model for an overview and adjustments would be possible. The simulation program, Siemens Plant Simulation 12 used in the construction of the complex model of the three flows, which where verified and validated against the real flows. Optimization on the simulation model was made with a high and a low demand for crankshafts. Several objects were taken into consideration as: minimal waiting processing Findel, minimal setup time and minimal total-PIA from a truly viable perspective. The optimization showed a possible production planning in order to best be able to run such large batches as possible with reduced readjustment time and for delays of production in processing rawflows to not occur in the refined flow. For maximum capacity in the company there are two different optimal solutions one solution focused on reducing setup time and the second solution to minimize the number of additional production hours per week. Discrete simulation of production flows are being used to support production planning and simulation model is created for the continued use of the Volvo GTO, either in simulation group or future researches and theses in collaboration with the University of Skövde. The project objectives were achieved with good results and resulted as a standing basis for future planning of batches and sequences of processing crankshaft Volvo GTO. Student thesisinfo:eu-repo/semantics/bachelorThesistexthttp://urn.kb.se/resolve?urn=urn:nbn:se:his:diva-11859application/pdfinfo:eu-repo/semantics/openAccess
collection NDLTD
language Swedish
format Others
sources NDLTD
topic Processing flows
throughput per hour
simulation model
changeovers
optimization
buffer
portal
operation
input data
buffer
cycle time
sequence
Bearbetning flöden
takt per timme
simuleringsmodell
omställningar
optimering
buffert
portal
operation
indata
lager
cykeltid
sekvens.
spellingShingle Processing flows
throughput per hour
simulation model
changeovers
optimization
buffer
portal
operation
input data
buffer
cycle time
sequence
Bearbetning flöden
takt per timme
simuleringsmodell
omställningar
optimering
buffert
portal
operation
indata
lager
cykeltid
sekvens.
Lundberg, Jesper
Mehtonen, Ronja
Utvärdering och analys av batchstorlekar, produktsekvenser och omställningstider
description Volvo GTO is one of the strongest brands in the truck industry, with a long and proud history of world-leading innovations. The factory in Skövde produces diesel engines of various sizes to Volvo GTO. The project has been carried out on the processing part of grovdel crankshaft. Where the objective was to construct a simulation model that reflects flows 0, 1 and 2 on the crankshaft grovdel order to produce the best driving style for the size of the batches and sequences, focusing on PIA, between the stock and conversion-up times. A theoretical study intervention gave knowledge to the methodology to ensure that the data is collected and processed correctly. The data were collected in an Excel document, which was integrated with the simulation model for an overview and adjustments would be possible. The simulation program, Siemens Plant Simulation 12 used in the construction of the complex model of the three flows, which where verified and validated against the real flows. Optimization on the simulation model was made with a high and a low demand for crankshafts. Several objects were taken into consideration as: minimal waiting processing Findel, minimal setup time and minimal total-PIA from a truly viable perspective. The optimization showed a possible production planning in order to best be able to run such large batches as possible with reduced readjustment time and for delays of production in processing rawflows to not occur in the refined flow. For maximum capacity in the company there are two different optimal solutions one solution focused on reducing setup time and the second solution to minimize the number of additional production hours per week. Discrete simulation of production flows are being used to support production planning and simulation model is created for the continued use of the Volvo GTO, either in simulation group or future researches and theses in collaboration with the University of Skövde. The project objectives were achieved with good results and resulted as a standing basis for future planning of batches and sequences of processing crankshaft Volvo GTO.
author Lundberg, Jesper
Mehtonen, Ronja
author_facet Lundberg, Jesper
Mehtonen, Ronja
author_sort Lundberg, Jesper
title Utvärdering och analys av batchstorlekar, produktsekvenser och omställningstider
title_short Utvärdering och analys av batchstorlekar, produktsekvenser och omställningstider
title_full Utvärdering och analys av batchstorlekar, produktsekvenser och omställningstider
title_fullStr Utvärdering och analys av batchstorlekar, produktsekvenser och omställningstider
title_full_unstemmed Utvärdering och analys av batchstorlekar, produktsekvenser och omställningstider
title_sort utvärdering och analys av batchstorlekar, produktsekvenser och omställningstider
publisher Högskolan i Skövde, Institutionen för ingenjörsvetenskap
publishDate 2015
url http://urn.kb.se/resolve?urn=urn:nbn:se:his:diva-11859
work_keys_str_mv AT lundbergjesper utvarderingochanalysavbatchstorlekarproduktsekvenserochomstallningstider
AT mehtonenronja utvarderingochanalysavbatchstorlekarproduktsekvenserochomstallningstider
AT lundbergjesper evaluationandanalysisofbatchsizesproductionsequencesandsetuptimes
AT mehtonenronja evaluationandanalysisofbatchsizesproductionsequencesandsetuptimes
_version_ 1718179167461179392