Summary: | 碩士 === 國立臺灣科技大學 === 建築系 === 104 === Abstract :
The most of contract mode in Taiwan are Design-Bid-Build
(DBB).The architecture or engineering firms commissioned by owner
will develop feasibility study, basic design and detail design,
at the same time, the contractor will not be decided before bidding
procedure. All the equipment and material will not be approved
by owner, those equipment size and interface location is not
confirmed neither. Hence, all the equipment size are designed size
in design phase, and not for real size in construction phase. You
have to do again CSD/SEM (Combined Service Drawing / Structure,
Electrical and,Mechanical)in construction phase, even though you
have done in design phase. The reason is all the equipment size
and interface location are different for both phases. All the
piping routine and direction will be revised again according to
approved equipment that provides real size and interface location,
and it will be resulted in CSD/SEM again for those revised piping.
In view of this, the BIM in design phase will be built for trunk
piping and bigger equipment in order to review space location and
line planning reasonability. This phase is not for planning branch
piping location, because the thing changed is often happened
during construction phase. Actually, the most of piping layout
in design phase are not sure for during construction phase. We
will discuss which level of development of BIM in design phase
that can be extended to the construction phase for continuous
utilization to avoid doing redundant effort without getting any
benefits from BIM.
|