Searching for an Optimal Construction Schedule with Compatible Financing Plans Using Multiobjective Optimization: Taking Taiwanese Construction Projects for Example

碩士 === 國立臺灣大學 === 土木工程學研究所 === 102 === For construction companies in Taiwan, low own funds and short-term financing are two of the financial characteristics, and financing from banks is a commonly-used way to obtain working capital during construction stage. To accurately estimate project costs and...

Full description

Bibliographic Details
Main Authors: Yu-Yi Chen, 陳佑怡
Other Authors: Po-Han Chen
Format: Others
Language:zh-TW
Published: 2014
Online Access:http://ndltd.ncl.edu.tw/handle/4z64k5
id ndltd-TW-102NTU05015181
record_format oai_dc
spelling ndltd-TW-102NTU050151812019-05-15T21:32:53Z http://ndltd.ncl.edu.tw/handle/4z64k5 Searching for an Optimal Construction Schedule with Compatible Financing Plans Using Multiobjective Optimization: Taking Taiwanese Construction Projects for Example 以多目標最佳化演算法找尋最適融資辦法之施工排程—以台灣營建工程為例 Yu-Yi Chen 陳佑怡 碩士 國立臺灣大學 土木工程學研究所 102 For construction companies in Taiwan, low own funds and short-term financing are two of the financial characteristics, and financing from banks is a commonly-used way to obtain working capital during construction stage. To accurately estimate project costs and conduct appropriate project financing plans are considered two important topics in the beginning stage of project’s life cycle. In this research, case study of Taiwanese construction project is analyzed by FPGA(Fast Pareto Genetic Algorithm), which combining construction financing and working capital into calculation to define an optimal construction schedule based on four objectives: Minimized total duration, minimized financing cost, minimized own funds, and maximized total profit. Verification is done by applying Enumeration method, Particle Swarm Optimization(PSO), and Simulated Annealing Arithmetic(SAA) to verify the credibility and reliability, and practicality of this proposed system. The results show that the optimal solution is equivalently to the top 20% located in the Pareto solutions, and FPGA can reduce nearly 99.99% of the total time spent. The system proposed in this study can assist construction companies in finding an optimal construction schedule with compatible financing plans and cash flows in the early project life cycle, and also facilitating the operation of construction financial plan and increasing efficiency in project management. Po-Han Chen 陳柏翰 2014 學位論文 ; thesis 141 zh-TW
collection NDLTD
language zh-TW
format Others
sources NDLTD
description 碩士 === 國立臺灣大學 === 土木工程學研究所 === 102 === For construction companies in Taiwan, low own funds and short-term financing are two of the financial characteristics, and financing from banks is a commonly-used way to obtain working capital during construction stage. To accurately estimate project costs and conduct appropriate project financing plans are considered two important topics in the beginning stage of project’s life cycle. In this research, case study of Taiwanese construction project is analyzed by FPGA(Fast Pareto Genetic Algorithm), which combining construction financing and working capital into calculation to define an optimal construction schedule based on four objectives: Minimized total duration, minimized financing cost, minimized own funds, and maximized total profit. Verification is done by applying Enumeration method, Particle Swarm Optimization(PSO), and Simulated Annealing Arithmetic(SAA) to verify the credibility and reliability, and practicality of this proposed system. The results show that the optimal solution is equivalently to the top 20% located in the Pareto solutions, and FPGA can reduce nearly 99.99% of the total time spent. The system proposed in this study can assist construction companies in finding an optimal construction schedule with compatible financing plans and cash flows in the early project life cycle, and also facilitating the operation of construction financial plan and increasing efficiency in project management.
author2 Po-Han Chen
author_facet Po-Han Chen
Yu-Yi Chen
陳佑怡
author Yu-Yi Chen
陳佑怡
spellingShingle Yu-Yi Chen
陳佑怡
Searching for an Optimal Construction Schedule with Compatible Financing Plans Using Multiobjective Optimization: Taking Taiwanese Construction Projects for Example
author_sort Yu-Yi Chen
title Searching for an Optimal Construction Schedule with Compatible Financing Plans Using Multiobjective Optimization: Taking Taiwanese Construction Projects for Example
title_short Searching for an Optimal Construction Schedule with Compatible Financing Plans Using Multiobjective Optimization: Taking Taiwanese Construction Projects for Example
title_full Searching for an Optimal Construction Schedule with Compatible Financing Plans Using Multiobjective Optimization: Taking Taiwanese Construction Projects for Example
title_fullStr Searching for an Optimal Construction Schedule with Compatible Financing Plans Using Multiobjective Optimization: Taking Taiwanese Construction Projects for Example
title_full_unstemmed Searching for an Optimal Construction Schedule with Compatible Financing Plans Using Multiobjective Optimization: Taking Taiwanese Construction Projects for Example
title_sort searching for an optimal construction schedule with compatible financing plans using multiobjective optimization: taking taiwanese construction projects for example
publishDate 2014
url http://ndltd.ncl.edu.tw/handle/4z64k5
work_keys_str_mv AT yuyichen searchingforanoptimalconstructionschedulewithcompatiblefinancingplansusingmultiobjectiveoptimizationtakingtaiwaneseconstructionprojectsforexample
AT chényòuyí searchingforanoptimalconstructionschedulewithcompatiblefinancingplansusingmultiobjectiveoptimizationtakingtaiwaneseconstructionprojectsforexample
AT yuyichen yǐduōmùbiāozuìjiāhuàyǎnsuànfǎzhǎoxúnzuìshìróngzībànfǎzhīshīgōngpáichéngyǐtáiwānyíngjiàngōngchéngwèilì
AT chényòuyí yǐduōmùbiāozuìjiāhuàyǎnsuànfǎzhǎoxúnzuìshìróngzībànfǎzhīshīgōngpáichéngyǐtáiwānyíngjiàngōngchéngwèilì
_version_ 1719116487423164416