Engineering Interface integration of monuments restoration-A case study on Assembly hall in The National Tainan Second Senior High School

碩士 === 國立成功大學 === 建築學系 === 102 === SUMMARY The main purpose of research is find out gap of monuments restoration between design and construction site. So this research is major to analyzed interface integration process of assembly hall in the National Tainan Second Senior High School monument resto...

Full description

Bibliographic Details
Main Authors: Tzu-ChiehHung, 洪姿捷
Other Authors: Tai-Nung Chen
Format: Others
Language:zh-TW
Published: 2014
Online Access:http://ndltd.ncl.edu.tw/handle/u6j76y
Description
Summary:碩士 === 國立成功大學 === 建築學系 === 102 === SUMMARY The main purpose of research is find out gap of monuments restoration between design and construction site. So this research is major to analyzed interface integration process of assembly hall in the National Tainan Second Senior High School monument restoration project to analysis interface conflict points of convergence process of design of repair, construction planning and construction site. Finally, propose interface integration principles. This result can improve efficiency construction of monuments restoration, quality of construction and generating cultural value. INTRODUCTION In recent years, the public and government awareness of the growing cultural preservation upgrade, so that monuments restoration increasing attention. It has cultural value of history, culture, art, science, which non-monetary can be measured. Then quality ensure will be very important. The monuments and the new architecture are not the same, and both projects different attributes. So the proposed management processes, steps and concepts are different. The quality of monuments restoration will be vary by professional training and concepts of owners, architects, construction supervision, site manager and craftsmen. Then quality of monuments restoration is no stability. The monuments restoration project participants are not entirely relevant experience who are all there. If junior officers such as repairing or re-use report writers, repair drawings drawing workers and the construction site managers lack experience, then they will continue to repeat the error, unable to get back from the repair process.   MATERIALS AND METHODS 1.The literature review approach To collect relevant domestic related literature like interface subject and monuments restoration, including Cultural Heritage Preservation Act , theses, books, journal articles, e-books, seminars and other literature data. Consolidate and analyzed and discussed in this study as a reference. 2.Examples of investigation approach Participate on Assembly hall in The National Tainan Second Senior High School the main structure restoration project. Analysis than the blueprint, supervision plan, construction plan with construction site the connect point. Well-documented case of all the major monuments restoration project processes and interface integration. 3.Interview survey approach Found the conflict points by involvement in The National Tainan Second Senior High School's auditorium the main structure restoration project. Interviews with professionals such as architects, construction supervision, site manager, craftsmen their practices and opinions. 4.Induction and analysis approach To analyzed interface integration of monuments restorations status of the various stages by the literature review approach. And the integration of the interface are summarized and analyzed by examples of investigation approach.   RESULTS AND DISCUSSION Monuments restoration has its interface management processes, but it still has its conflict points. Summarized monuments restoration interface issue between design and construction by the described of interface issue in Table interface conflict treatment. As follows: 1.Construction plan lacks integrity 2.Construct process of construction site are different with process of construction plan 3.Drawing size are different with construction site 4.Materials and design drawing be differently used by construction site Among the interface management, there will be some unexpected conflict points. There should know how to make better by coordination, integration and test. Construction plans include labor arrangements, required of construction equipment, materials and job progress. From this interface management is inseparable from the Labor, places, things, and Time the five factors. Discuss analysis of interface management and results of treatment by literature collection, participation project and access. Listed principles of interface integrate of monuments restoration project. As follows: 1.Integration Concept 2.Participants should be professional 3.Management of figure is required 4.Design changes in a timely manner 5.Restoration method to strive excellence 6.The static and dynamic treatment need to implement 7.Information feedback mechanism established Above principles of monuments restoration, implementing in the monuments restoration project. From the design and plan phase to the final maintenance and management. Restoration concept by architect explain this project. Using figure management does to improve issue of construction plan of contractor. Let monuments restoration project through the interface integration of static and dynamic will fall interface issues to the lowest. Also use information feedback mechanism to provide monuments restoration project reference processes and record data. By the above restoration principle, there will be able to effectively improve the efficiency and quality of construction of monument restoration project.   CONCLUSION Integration discussion and analysis section of the above. This study compilation and analysis by literature, and explore the cultural value of monuments. Build interface integration-process of comparison table and the construction process of actual project of monuments restoration project. Finally, propose principles of interface integration of monuments restoration project. Then can get the following conclusions: 1.The bad communication reasons between monuments restoration of design and construction site. 2.Parsing process of interface integration of monuments restoration project, then propose principles of interface integration. 3.Recording data of the project by forms and available for subsequent reference to the use of monuments restoration project. Completely plans and construction drawings will effectively reduce the interface of construction, thereby reducing construction costs and enhancing efficiency and quality of construction. Finally, we can effectively repair and reuse monuments while generating cultural value.