Summary: | 碩士 === 中國文化大學 === 機械工程學系數位機電碩士班 === 101 === This thesis is divided into three parts: the system establishment and
inspection technique, maintenance procedure set up and enhance the wind
turbine performance.
The wind turbine which we used to study in here is 1.8~2.4 KW
wind turbine in P.C.C.U. Campus—installed since 2008.The power is
already cumulated 4020.7kwh.
Through LabView/the man-machine interface, we process in
real-time monitoring on line by campus network. We have three stages
maintenance—every day (immediate inspection), three month (quarter
inspection) and every one year (annual inspection).
In performance improvement topic in here ,we through the
implementation of NSC Project” Home-Made 3-D Image Measuring
Instrument” to integrate a 3D blade scan platform to obtain the profile of
the blade airfoil 3D model, then put aerodynamic parameters into existing
mathematical model to enhance the energy conversion coefficient as a
basis for future improvement.
|