Earned Value Management Applied to The Pilot Run of Hot Stamping Production Line

碩士 === 國立成功大學 === 工學院工程管理碩士在職專班 === 101 === Conventional project management considers only about the actual budget costs and planned budget costs, yet ignores the progress information. These parameters cannot provide explanations about the differences are derived from the delay of progress or cost o...

Full description

Bibliographic Details
Main Authors: Wan-YunHuang, 黃菀筠
Other Authors: Heiu-Jou Shaw
Format: Others
Language:zh-TW
Published: 2013
Online Access:http://ndltd.ncl.edu.tw/handle/n5nbz4
id ndltd-TW-101NCKU5031061
record_format oai_dc
spelling ndltd-TW-101NCKU50310612019-05-15T21:03:44Z http://ndltd.ncl.edu.tw/handle/n5nbz4 Earned Value Management Applied to The Pilot Run of Hot Stamping Production Line 實獲值管理在熱沖壓試作產線建置專案之應用 Wan-YunHuang 黃菀筠 碩士 國立成功大學 工學院工程管理碩士在職專班 101 Conventional project management considers only about the actual budget costs and planned budget costs, yet ignores the progress information. These parameters cannot provide explanations about the differences are derived from the delay of progress or cost overruns and savings. Therefore lacks basis information for decision-making and further project improvements. This study applied project management approach to the establishment of hot stamping pilot run production line, by recording costs and progress information for further analysis, and combining with Earned Value Management, to explore the subsequence feasibility and meaning. The result shows that Earned Value Management does enhance the progress control and the early risk detecting. With the analysis of costs and progress variation, information can be provided for resource allocation, overtime decision-making, and gap correction, therefore completing the project on time. Heiu-Jou Shaw 邵揮洲 2013 學位論文 ; thesis 68 zh-TW
collection NDLTD
language zh-TW
format Others
sources NDLTD
description 碩士 === 國立成功大學 === 工學院工程管理碩士在職專班 === 101 === Conventional project management considers only about the actual budget costs and planned budget costs, yet ignores the progress information. These parameters cannot provide explanations about the differences are derived from the delay of progress or cost overruns and savings. Therefore lacks basis information for decision-making and further project improvements. This study applied project management approach to the establishment of hot stamping pilot run production line, by recording costs and progress information for further analysis, and combining with Earned Value Management, to explore the subsequence feasibility and meaning. The result shows that Earned Value Management does enhance the progress control and the early risk detecting. With the analysis of costs and progress variation, information can be provided for resource allocation, overtime decision-making, and gap correction, therefore completing the project on time.
author2 Heiu-Jou Shaw
author_facet Heiu-Jou Shaw
Wan-YunHuang
黃菀筠
author Wan-YunHuang
黃菀筠
spellingShingle Wan-YunHuang
黃菀筠
Earned Value Management Applied to The Pilot Run of Hot Stamping Production Line
author_sort Wan-YunHuang
title Earned Value Management Applied to The Pilot Run of Hot Stamping Production Line
title_short Earned Value Management Applied to The Pilot Run of Hot Stamping Production Line
title_full Earned Value Management Applied to The Pilot Run of Hot Stamping Production Line
title_fullStr Earned Value Management Applied to The Pilot Run of Hot Stamping Production Line
title_full_unstemmed Earned Value Management Applied to The Pilot Run of Hot Stamping Production Line
title_sort earned value management applied to the pilot run of hot stamping production line
publishDate 2013
url http://ndltd.ncl.edu.tw/handle/n5nbz4
work_keys_str_mv AT wanyunhuang earnedvaluemanagementappliedtothepilotrunofhotstampingproductionline
AT huángwǎnyún earnedvaluemanagementappliedtothepilotrunofhotstampingproductionline
AT wanyunhuang shíhuòzhíguǎnlǐzàirèchōngyāshìzuòchǎnxiànjiànzhìzhuānànzhīyīngyòng
AT huángwǎnyún shíhuòzhíguǎnlǐzàirèchōngyāshìzuòchǎnxiànjiànzhìzhuānànzhīyīngyòng
_version_ 1719109741672660992