Scheduling Project Tasks under Resource Constrained using Design Structure Matrix and Quality Equations

碩士 === 國立臺灣科技大學 === 營建工程系 === 97 === Design phase is characterized by highly coupled and interdependent activities, which result rework or iteration in this phase. In dealing with this problem, information flows have to be well organized, so it can lead to the most optimum completion time. The Depen...

Full description

Bibliographic Details
Main Authors: Theresia Daisy Nattali Suparman, 陳戴幸
Other Authors: Sou Sen Leu
Format: Others
Language:en_US
Published: 2009
Online Access:http://ndltd.ncl.edu.tw/handle/06369888115901612781
id ndltd-TW-097NTUS5512035
record_format oai_dc
spelling ndltd-TW-097NTUS55120352016-05-02T04:11:39Z http://ndltd.ncl.edu.tw/handle/06369888115901612781 Scheduling Project Tasks under Resource Constrained using Design Structure Matrix and Quality Equations SchedulingProjectTasksunderResourceConstrainedusingDesignStructureMatrixandQualityEquations Theresia Daisy Nattali Suparman 陳戴幸 碩士 國立臺灣科技大學 營建工程系 97 Design phase is characterized by highly coupled and interdependent activities, which result rework or iteration in this phase. In dealing with this problem, information flows have to be well organized, so it can lead to the most optimum completion time. The Dependency Structure Matrix (DSM) is a compact matrix representation that models information flows among activities in the design phase. Previous DSM concepts used basic logic of faster and fewer iteration, while assuming the number of iteration occurred to achieve optimum completion time. This thesis proposed a new methodology which combined faster and fewer iteration concepts with adding other information, i.e. Quality Equations. Quality Equations will be performed in order to reduce the lack of assumption in determining the number of iteration occurred. Resource constrained problem is also added in the thesis to make the problem close to the reality. To help coordinate/optimize the activities structure in terms of minimizing completion time, Genetic Algorithm (GA) will be conducted in this thesis. As the result, combining DSM with quality equations give more accurate expected duration since assumption regarding the number of iteration for each task can be replaced by exact number revealed from quality equations. Sou Sen Leu 呂守陞 2009 學位論文 ; thesis 130 en_US
collection NDLTD
language en_US
format Others
sources NDLTD
description 碩士 === 國立臺灣科技大學 === 營建工程系 === 97 === Design phase is characterized by highly coupled and interdependent activities, which result rework or iteration in this phase. In dealing with this problem, information flows have to be well organized, so it can lead to the most optimum completion time. The Dependency Structure Matrix (DSM) is a compact matrix representation that models information flows among activities in the design phase. Previous DSM concepts used basic logic of faster and fewer iteration, while assuming the number of iteration occurred to achieve optimum completion time. This thesis proposed a new methodology which combined faster and fewer iteration concepts with adding other information, i.e. Quality Equations. Quality Equations will be performed in order to reduce the lack of assumption in determining the number of iteration occurred. Resource constrained problem is also added in the thesis to make the problem close to the reality. To help coordinate/optimize the activities structure in terms of minimizing completion time, Genetic Algorithm (GA) will be conducted in this thesis. As the result, combining DSM with quality equations give more accurate expected duration since assumption regarding the number of iteration for each task can be replaced by exact number revealed from quality equations.
author2 Sou Sen Leu
author_facet Sou Sen Leu
Theresia Daisy Nattali Suparman
陳戴幸
author Theresia Daisy Nattali Suparman
陳戴幸
spellingShingle Theresia Daisy Nattali Suparman
陳戴幸
Scheduling Project Tasks under Resource Constrained using Design Structure Matrix and Quality Equations
author_sort Theresia Daisy Nattali Suparman
title Scheduling Project Tasks under Resource Constrained using Design Structure Matrix and Quality Equations
title_short Scheduling Project Tasks under Resource Constrained using Design Structure Matrix and Quality Equations
title_full Scheduling Project Tasks under Resource Constrained using Design Structure Matrix and Quality Equations
title_fullStr Scheduling Project Tasks under Resource Constrained using Design Structure Matrix and Quality Equations
title_full_unstemmed Scheduling Project Tasks under Resource Constrained using Design Structure Matrix and Quality Equations
title_sort scheduling project tasks under resource constrained using design structure matrix and quality equations
publishDate 2009
url http://ndltd.ncl.edu.tw/handle/06369888115901612781
work_keys_str_mv AT theresiadaisynattalisuparman schedulingprojecttasksunderresourceconstrainedusingdesignstructurematrixandqualityequations
AT chéndàixìng schedulingprojecttasksunderresourceconstrainedusingdesignstructurematrixandqualityequations
_version_ 1718254249893167104