Performing Time-Cost Trade-Off Analysis via FMGA-Simulation Mechanism
碩士 === 朝陽科技大學 === 營建工程系碩士班 === 95 === Construction project is composed of a network of activities. To perform the activities of a project, construction planners usually can select construction methods or technologies and associated resources including crew sizes and equipment. Different construction...