Summary: | 碩士 === 國立臺灣科技大學 === 營建工程系 === 93 === Project durations and costs contain uncertainties, however, the uncertainties are usually neglected in project cash-flow. Accordingly, this research proposes “Simulation of Construction Project Cash-Flow Model”, which considers factor periods and rate retardation to improve the uncertainty analyses of construction project cash-flow. Variation were found to expend when factor periods and rate retardation were considered after testing. With model, contractors can forecast the project cash-flow reasonably, moreover, the results can be reference for contractors to bid, performance risk management, and prepare the plan of dispatch project capital.
|