THE DEVELOPMENT OF REACTIVE SCHEDULING ALGORITHM FOR THE JOB- SHOPTYPE FACTORY UNDER ABNORMAL SITUATION

碩士 === 元智工學院 === 工業工程學系 === 84 === This research is to investigate the most incurring problem , " the exchange ofthe manufacturing orders" , in the dynamic scheduling of the shop floor.As theresults , the causes and effects of these disturb...

Full description

Bibliographic Details
Main Authors: WU, BEN-YU, 吳斌友
Other Authors: Pei-chann Chang
Format: Others
Language:zh-TW
Online Access:http://ndltd.ncl.edu.tw/handle/28231818164393076534
Description
Summary:碩士 === 元智工學院 === 工業工程學系 === 84 === This research is to investigate the most incurring problem , " the exchange ofthe manufacturing orders" , in the dynamic scheduling of the shop floor.As theresults , the causes and effects of these disturbances can be furthercategorized and analyzed . Therefor , the impacts of each disturbances to theoriginal schedule can be clearly identified . Then , a reactive schedulingalgorithm is to be developed to efficiently and efficiently resolve theimpacts caused by the disturbances on the shop floor. As the solution to theimpacts of the disturbances , we can mimic the logic applied in MRP, i.e., netchange, and regenerate. The computation time in net change is small while thesolution quality is rough and near-sighted . As in regenerate , the solutiontime is cos tly while the solution quality is closed to optimality . Base onthe " net change " in MRP , we will develop a "Change-Order" method. When "theexchange of manufacturing orders " happens , it can analyze the disturbancesand generate a new feasible schedule rapidly . This result is better thenusing the " Fix-Order " method . Especially on the control for the delayingorders . Also , we will find a feasible solution to clinch " rush orders "problems which factories are often incurring.