Summary: | 碩士 === 國立台灣工業技術學院 === 工程技術研究所 === 84 === In traditional bidding system, contracts are awarded
exclusively on pricebasis. Innovative approaches that try to
integrate cost, time, quality, andsafety factors in bidder
evaluation have been studied in these years. Pros and cons of
these approaches are discussed to serve as a base of this
research. For projects that time value can properly be
estimated, a cost plus time value meth-od is recommended.
Otherwise an analytical hierarchical process (AHP) is sug-gested
to determine weightings for cost, time, quality, and other facto
良式towners wish to encompass in bidder evaluation. A public
housing project is us\edas an example in this research to
explore potential benefits as well as problemsof proposed
approaches. Questionnaires for AHP,methods for calculating
weight-ings for each factors, computational process to establish
an integrated index for bidder evalution are illustrated.
|