Study on the application of shutdown factors to investment management of 35 kV and above power grid infrastructure projects
With the strengthening of external supervision and the management requirements of internal quality and efficiency improvement of power grid, it is particularly important to improve the lean level of power grid investment. However, the accuracy and scientificity of the current grid infrastructure pro...
Main Authors: | , , , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
EDP Sciences
2021-01-01
|
Series: | E3S Web of Conferences |
Online Access: | https://www.e3s-conferences.org/articles/e3sconf/pdf/2021/09/e3sconf_iaecst20_01015.pdf |
id |
doaj-f3f1d3d0c056402bbd9ddcd94528f7ae |
---|---|
record_format |
Article |
spelling |
doaj-f3f1d3d0c056402bbd9ddcd94528f7ae2021-02-01T08:06:18ZengEDP SciencesE3S Web of Conferences2267-12422021-01-012330101510.1051/e3sconf/202123301015e3sconf_iaecst20_01015Study on the application of shutdown factors to investment management of 35 kV and above power grid infrastructure projectsZhou Ming0Lu Shengwei1Wu Qiang2Jin Sha3Yan Jiong4Sang Zixia5State Grid Hubei Electric Power Co., LtdState Grid Hubei Electric Power Co., LtdState Grid Hubei Electric Power Co., LtdState Grid Hubei Electric Power Co., LtdHubei Economic Research Institute of State Grid Hubei Electric Power Co., LtdHubei Economic Research Institute of State Grid Hubei Electric Power Co., LtdWith the strengthening of external supervision and the management requirements of internal quality and efficiency improvement of power grid, it is particularly important to improve the lean level of power grid investment. However, the accuracy and scientificity of the current grid infrastructure project investment plan adjustment need to be further improved, and the basis for the completion of investment submission is the on-site construction progress. Therefore, this topic carries out the analysis of the factors affecting the construction progress, including the types of the factors affecting the construction, the depth and breadth of the impact, and the impact of the milestone stage, and takes the analysis results of the shutdown factors as the reference basis for the adjustment of the investment plan, so as to improve the investment management level of the company.https://www.e3s-conferences.org/articles/e3sconf/pdf/2021/09/e3sconf_iaecst20_01015.pdf |
collection |
DOAJ |
language |
English |
format |
Article |
sources |
DOAJ |
author |
Zhou Ming Lu Shengwei Wu Qiang Jin Sha Yan Jiong Sang Zixia |
spellingShingle |
Zhou Ming Lu Shengwei Wu Qiang Jin Sha Yan Jiong Sang Zixia Study on the application of shutdown factors to investment management of 35 kV and above power grid infrastructure projects E3S Web of Conferences |
author_facet |
Zhou Ming Lu Shengwei Wu Qiang Jin Sha Yan Jiong Sang Zixia |
author_sort |
Zhou Ming |
title |
Study on the application of shutdown factors to investment management of 35 kV and above power grid infrastructure projects |
title_short |
Study on the application of shutdown factors to investment management of 35 kV and above power grid infrastructure projects |
title_full |
Study on the application of shutdown factors to investment management of 35 kV and above power grid infrastructure projects |
title_fullStr |
Study on the application of shutdown factors to investment management of 35 kV and above power grid infrastructure projects |
title_full_unstemmed |
Study on the application of shutdown factors to investment management of 35 kV and above power grid infrastructure projects |
title_sort |
study on the application of shutdown factors to investment management of 35 kv and above power grid infrastructure projects |
publisher |
EDP Sciences |
series |
E3S Web of Conferences |
issn |
2267-1242 |
publishDate |
2021-01-01 |
description |
With the strengthening of external supervision and the management requirements of internal quality and efficiency improvement of power grid, it is particularly important to improve the lean level of power grid investment. However, the accuracy and scientificity of the current grid infrastructure project investment plan adjustment need to be further improved, and the basis for the completion of investment submission is the on-site construction progress. Therefore, this topic carries out the analysis of the factors affecting the construction progress, including the types of the factors affecting the construction, the depth and breadth of the impact, and the impact of the milestone stage, and takes the analysis results of the shutdown factors as the reference basis for the adjustment of the investment plan, so as to improve the investment management level of the company. |
url |
https://www.e3s-conferences.org/articles/e3sconf/pdf/2021/09/e3sconf_iaecst20_01015.pdf |
work_keys_str_mv |
AT zhouming studyontheapplicationofshutdownfactorstoinvestmentmanagementof35kvandabovepowergridinfrastructureprojects AT lushengwei studyontheapplicationofshutdownfactorstoinvestmentmanagementof35kvandabovepowergridinfrastructureprojects AT wuqiang studyontheapplicationofshutdownfactorstoinvestmentmanagementof35kvandabovepowergridinfrastructureprojects AT jinsha studyontheapplicationofshutdownfactorstoinvestmentmanagementof35kvandabovepowergridinfrastructureprojects AT yanjiong studyontheapplicationofshutdownfactorstoinvestmentmanagementof35kvandabovepowergridinfrastructureprojects AT sangzixia studyontheapplicationofshutdownfactorstoinvestmentmanagementof35kvandabovepowergridinfrastructureprojects |
_version_ |
1724315605807398912 |