Resource Tardiness Weighted Cost Minimization in Project Scheduling
In this paper, we study a project scheduling problem that is called resource constrained project scheduling problem under minimization of total weighted resource tardiness penalty cost (RCPSP-TWRTPC). In this problem, the project is subject to renewable resources, each renewable resource is availabl...
Main Author: | Ali Shirzadeh Chaleshtari |
---|---|
Format: | Article |
Language: | English |
Published: |
Hindawi Limited
2017-01-01
|
Series: | Advances in Operations Research |
Online Access: | http://dx.doi.org/10.1155/2017/1308704 |
Similar Items
-
Corrigendum to “Resource Tardiness Weighted Cost Minimization in Project Scheduling”
by: Ali Shirzadeh Chaleshtari
Published: (2017-01-01) -
A hybrid GRASP algorithm for minimizing total weighted resource tardiness penalty costs in scheduling of project networks
by: M. Ranjbar
Published: (2012-09-01) -
Minimizing Total Resource Tardiness Penalty Costs in the Resource Constrained Project Scheduling Problem with Metaheuristic Algorithms
by: R. Golestaneh, et al.
Published: (2013-09-01) -
Scheduling Open Shops to Minimize Total Weighted Tardiness
by: An-Hsiang Lin, et al.
Published: (2000) -
Minimizing Tardiness Penalty Costs in Job Shop Scheduling Under Maximum Allowable Tardiness
by: Jae-Gon Kim, et al.
Published: (2020-11-01)