DETERMINATION OF CRITICAL PATTERN OF 60 METER SHIP CONSTRUCTION PROJECT USING PRECEDENCE DIAGRAM METHOD (PDM)
PT. XYZ in Surabaya is engaged in the production of commercial ships, providing ship repair and maintenance services as well as general engineering with specifications based on orders. Along with the development of the technology industry, ship production requires every shipyard to evaluate the s...
Main Authors: | I Nengah Putra APRIYANTO, Suyono THAMRIN, Edi SUHARDONO, Beny RUDIAWAN, Arica Dwi SUSANTO |
---|---|
Format: | Article |
Language: | English |
Published: |
Regional Department of Defense Resources Management Studies
2019-10-01
|
Series: | Journal of Defense Resources Management |
Subjects: | |
Online Access: | http://www.jodrm.eu/issues/Volume10_issue2/09_EARNED%20VALUE%20METHOD_Nengah%20Putra%20Apriyanto_INDO.pdf |
Similar Items
-
PROJECT SCHEDULING ANALYSIS USING PRECEDENCE DIAGRAM METHOD (PDM)
by: Andani Devi Novitasari, et al.
Published: (2018-10-01) -
PDM-ProValue meets cardiovascular outcome trials in diabetes
by: Katharina Fritzen, et al.
Published: (2019-01-01) -
PDM Field Study in Collaborative Engineering Education – Results from 2016/17
by: Andreas Probst, et al.
Published: (2019-02-01) -
ABOUT APPROACHES OF CREATION OF INTEGRATED INFORMATION SYSTEM PDM-ERP
by: V. G. Mikhailov
Published: (2016-07-01) -
A Novel Phase Noise Suppression Scheme Utilizing Gaussian Wavelet Basis Expansion for PDM CO-OFDM Superchannel
by: Yuanxiang Chen, et al.
Published: (2020-01-01)