Sub-activity Time-Cost Trade-off Model of Building Structural Beam on the Projects in the North Aceh Region
Problems for both delayed and accelerated activities in scheduling are common in most projects. This problem can implicate on the additional construction cost with different trends as a specific model. A model can provide valuable information to project acceleration judgement. This research aims to...
Main Authors: | , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
Syiah Kuala University
2019-08-01
|
Series: | Aceh International Journal of Science and Technology |
Subjects: | |
Online Access: | http://jurnal.unsyiah.ac.id/AIJST/article/view/13218 |
id |
doaj-ca1db4c09d9b4dc49f72dcd89d92badc |
---|---|
record_format |
Article |
spelling |
doaj-ca1db4c09d9b4dc49f72dcd89d92badc2020-11-25T01:19:49ZengSyiah Kuala UniversityAceh International Journal of Science and Technology2088-98602019-08-0182869410.13170/aijst.8.2.1321810268Sub-activity Time-Cost Trade-off Model of Building Structural Beam on the Projects in the North Aceh RegionFachrurrazi Fachrurrazi0Abdullah Abdullah1Yuwaldi Away2Teuku Budi Aulia3Syiah Kuala UniversityDepartment of Civil Engineering, Universitas Syiah KualaDepartment of Electrical Engineering, Universitas Syiah KualaDepartment of Civil Engineering, Universitas Syiah KualaProblems for both delayed and accelerated activities in scheduling are common in most projects. This problem can implicate on the additional construction cost with different trends as a specific model. A model can provide valuable information to project acceleration judgement. This research aims to develop the TCTO sub-activity model of formwork, rebar work, and concrete work of the building structural beam on the projects in the North Aceh region. We have collected 33 data sourced from the project cost plan report and respondents judgment in the reviewed area. Descriptive statistics and the regression analysis are used to generate the TCTO model. The results show that the activity duration of the structural beam as broken down into sub-activities of formwork, rebar work and concrete work can be compressed until reaching 40%, 50%, and 40% of its normal duration, respectively. The additional cost of the compressed duration for each sub-activity shows the direct incremental cost per days of 3.67%, 3.63%, and 4.27% of its normal cost. Meanwhile, the possible crash cost of each the sub-activities are 122%, 118.15%, 125.61%, respectively. The models practically represent a linear model in the same daily pattern acceleration.http://jurnal.unsyiah.ac.id/AIJST/article/view/13218compressed durationadditional costlinear tcto activity modelreinforced concretebuilding beam structure |
collection |
DOAJ |
language |
English |
format |
Article |
sources |
DOAJ |
author |
Fachrurrazi Fachrurrazi Abdullah Abdullah Yuwaldi Away Teuku Budi Aulia |
spellingShingle |
Fachrurrazi Fachrurrazi Abdullah Abdullah Yuwaldi Away Teuku Budi Aulia Sub-activity Time-Cost Trade-off Model of Building Structural Beam on the Projects in the North Aceh Region Aceh International Journal of Science and Technology compressed duration additional cost linear tcto activity model reinforced concrete building beam structure |
author_facet |
Fachrurrazi Fachrurrazi Abdullah Abdullah Yuwaldi Away Teuku Budi Aulia |
author_sort |
Fachrurrazi Fachrurrazi |
title |
Sub-activity Time-Cost Trade-off Model of Building Structural Beam on the Projects in the North Aceh Region |
title_short |
Sub-activity Time-Cost Trade-off Model of Building Structural Beam on the Projects in the North Aceh Region |
title_full |
Sub-activity Time-Cost Trade-off Model of Building Structural Beam on the Projects in the North Aceh Region |
title_fullStr |
Sub-activity Time-Cost Trade-off Model of Building Structural Beam on the Projects in the North Aceh Region |
title_full_unstemmed |
Sub-activity Time-Cost Trade-off Model of Building Structural Beam on the Projects in the North Aceh Region |
title_sort |
sub-activity time-cost trade-off model of building structural beam on the projects in the north aceh region |
publisher |
Syiah Kuala University |
series |
Aceh International Journal of Science and Technology |
issn |
2088-9860 |
publishDate |
2019-08-01 |
description |
Problems for both delayed and accelerated activities in scheduling are common in most projects. This problem can implicate on the additional construction cost with different trends as a specific model. A model can provide valuable information to project acceleration judgement. This research aims to develop the TCTO sub-activity model of formwork, rebar work, and concrete work of the building structural beam on the projects in the North Aceh region. We have collected 33 data sourced from the project cost plan report and respondents judgment in the reviewed area. Descriptive statistics and the regression analysis are used to generate the TCTO model. The results show that the activity duration of the structural beam as broken down into sub-activities of formwork, rebar work and concrete work can be compressed until reaching 40%, 50%, and 40% of its normal duration, respectively. The additional cost of the compressed duration for each sub-activity shows the direct incremental cost per days of 3.67%, 3.63%, and 4.27% of its normal cost. Meanwhile, the possible crash cost of each the sub-activities are 122%, 118.15%, 125.61%, respectively. The models practically represent a linear model in the same daily pattern acceleration. |
topic |
compressed duration additional cost linear tcto activity model reinforced concrete building beam structure |
url |
http://jurnal.unsyiah.ac.id/AIJST/article/view/13218 |
work_keys_str_mv |
AT fachrurrazifachrurrazi subactivitytimecosttradeoffmodelofbuildingstructuralbeamontheprojectsinthenorthacehregion AT abdullahabdullah subactivitytimecosttradeoffmodelofbuildingstructuralbeamontheprojectsinthenorthacehregion AT yuwaldiaway subactivitytimecosttradeoffmodelofbuildingstructuralbeamontheprojectsinthenorthacehregion AT teukubudiaulia subactivitytimecosttradeoffmodelofbuildingstructuralbeamontheprojectsinthenorthacehregion |
_version_ |
1725137187923558400 |