Development of Changeover Operating Method Based on Performance Prediction of Hybrid Geothermal Heat Pump Systems through Field Test and Numerical Analysis

The installation and operation of geothermal systems increased due to the expectation of good cooling and heating performance due to stable heat source temperatures. In actual geothermal system operations, heat source temperature rises or falls due to an imbalance of heating and cooling energy usage...

Full description

Bibliographic Details
Main Authors: Ji-Hyun Shin, Yoon-Bok Seong, Yong-In Kim, Young-Hum Cho
Format: Article
Language:English
Published: MDPI AG 2020-10-01
Series:Energies
Subjects:
Online Access:https://www.mdpi.com/1996-1073/13/20/5333
Description
Summary:The installation and operation of geothermal systems increased due to the expectation of good cooling and heating performance due to stable heat source temperatures. In actual geothermal system operations, heat source temperature rises or falls due to an imbalance of heating and cooling energy usage. Problems of source side temperature result in reduced geothermal system performance. The purpose of this study is to develop hybrid geothermal system operation technology to stabilize temperature and improve system performance by utilizing auxiliary heat source system. The auxiliary heat source system is operated by comparing the performance when operating the geothermal heat pump system alone and the performance when operating the hybrid geothermal heat pump system. The performance of a hybrid geothermal system is determined by the circulating water temperature of the geothermal system and the circulating water temperature of the auxiliary heat source system. Hybrid geothermal heat pump system performance is predicted through numerical analysis and collection of hybrid geothermal system performance data at various temperature ranges through field test. An operating method was developed using the predicted performance as the changeover operating point of the hybrid geothermal heat pump system. When applying the development and operation technology, it handled about 11% more load than the existing geothermal system operation. The addition of an auxiliary heat source increases the initial investment cost compared to the existing geothermal system, but decreases energy consumption, confirming that the initial investment cost of 15.3 years is recovered.
ISSN:1996-1073