Plugging and Its Stability Evaluation for the Ore Pass in the Nonempty Condition Based on Controllable Grouting of Cement-Sodium Silicate Grout

Aimed at the problem to plug the main ore pass with the large collapse at Xingshan Iron Mine, the viscosity-time test and the heap perfusion test of cement-silicate grout in a loose rock mass are carried out. The relationship between the vertical diffusion distance of cement-silicate grout and setti...

Full description

Bibliographic Details
Main Authors: Ye Yuan, Dengpan Qiao, Shibo Yu
Format: Article
Language:English
Published: Hindawi-Wiley 2021-01-01
Series:Geofluids
Online Access:http://dx.doi.org/10.1155/2021/6666297
id doaj-a0e6fa6232094cd191dff1f5b8b63460
record_format Article
spelling doaj-a0e6fa6232094cd191dff1f5b8b634602021-02-15T12:52:49ZengHindawi-WileyGeofluids1468-81151468-81232021-01-01202110.1155/2021/66662976666297Plugging and Its Stability Evaluation for the Ore Pass in the Nonempty Condition Based on Controllable Grouting of Cement-Sodium Silicate GroutYe Yuan0Dengpan Qiao1Shibo Yu2Faculty of Land Resources Engineering, Kunming University of Science and Technology, Kunming, Yunnan 650093, ChinaFaculty of Land Resources Engineering, Kunming University of Science and Technology, Kunming, Yunnan 650093, ChinaBGRIMM Technology Group, Beijing 100160, ChinaAimed at the problem to plug the main ore pass with the large collapse at Xingshan Iron Mine, the viscosity-time test and the heap perfusion test of cement-silicate grout in a loose rock mass are carried out. The relationship between the vertical diffusion distance of cement-silicate grout and setting time of grout is studied, and research results are applied to the design of plugging engineering of the main ore pass in -330 m. Based on the numerical simulation of the plugging structure and the long-term stress monitoring of the cable sensors, the stability of the plugging structure itself and the control for the movement of shafts nearby are comprehensively evaluated. The test results show that for a specific loose rock mass, the vertical diffusion distance of cement-silicate grout in the loose rock mass is a power function of grout setting time. Based on the design concept to plug the main ore pass with the large collapse using artificially constructed “bite-bonded arch,” the plugging design and construction procedures are proposed. A numerical model and long-term monitoring of cable stress show that the plugging structure is stable and has an obvious effect on the control movement of abutment shafts.http://dx.doi.org/10.1155/2021/6666297
collection DOAJ
language English
format Article
sources DOAJ
author Ye Yuan
Dengpan Qiao
Shibo Yu
spellingShingle Ye Yuan
Dengpan Qiao
Shibo Yu
Plugging and Its Stability Evaluation for the Ore Pass in the Nonempty Condition Based on Controllable Grouting of Cement-Sodium Silicate Grout
Geofluids
author_facet Ye Yuan
Dengpan Qiao
Shibo Yu
author_sort Ye Yuan
title Plugging and Its Stability Evaluation for the Ore Pass in the Nonempty Condition Based on Controllable Grouting of Cement-Sodium Silicate Grout
title_short Plugging and Its Stability Evaluation for the Ore Pass in the Nonempty Condition Based on Controllable Grouting of Cement-Sodium Silicate Grout
title_full Plugging and Its Stability Evaluation for the Ore Pass in the Nonempty Condition Based on Controllable Grouting of Cement-Sodium Silicate Grout
title_fullStr Plugging and Its Stability Evaluation for the Ore Pass in the Nonempty Condition Based on Controllable Grouting of Cement-Sodium Silicate Grout
title_full_unstemmed Plugging and Its Stability Evaluation for the Ore Pass in the Nonempty Condition Based on Controllable Grouting of Cement-Sodium Silicate Grout
title_sort plugging and its stability evaluation for the ore pass in the nonempty condition based on controllable grouting of cement-sodium silicate grout
publisher Hindawi-Wiley
series Geofluids
issn 1468-8115
1468-8123
publishDate 2021-01-01
description Aimed at the problem to plug the main ore pass with the large collapse at Xingshan Iron Mine, the viscosity-time test and the heap perfusion test of cement-silicate grout in a loose rock mass are carried out. The relationship between the vertical diffusion distance of cement-silicate grout and setting time of grout is studied, and research results are applied to the design of plugging engineering of the main ore pass in -330 m. Based on the numerical simulation of the plugging structure and the long-term stress monitoring of the cable sensors, the stability of the plugging structure itself and the control for the movement of shafts nearby are comprehensively evaluated. The test results show that for a specific loose rock mass, the vertical diffusion distance of cement-silicate grout in the loose rock mass is a power function of grout setting time. Based on the design concept to plug the main ore pass with the large collapse using artificially constructed “bite-bonded arch,” the plugging design and construction procedures are proposed. A numerical model and long-term monitoring of cable stress show that the plugging structure is stable and has an obvious effect on the control movement of abutment shafts.
url http://dx.doi.org/10.1155/2021/6666297
work_keys_str_mv AT yeyuan plugginganditsstabilityevaluationfortheorepassinthenonemptyconditionbasedoncontrollablegroutingofcementsodiumsilicategrout
AT dengpanqiao plugginganditsstabilityevaluationfortheorepassinthenonemptyconditionbasedoncontrollablegroutingofcementsodiumsilicategrout
AT shiboyu plugginganditsstabilityevaluationfortheorepassinthenonemptyconditionbasedoncontrollablegroutingofcementsodiumsilicategrout
_version_ 1714867037098999808