Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia

Any construction project, even one that is excellently planned and organized, is prone to the risk of unforeseen events and problems, which in effect can cause late completion of works. The paper presents the results of the research conducted among Polish and Slovakian building contractors. One atte...

Full description

Bibliographic Details
Main Authors: Agnieszka Leśniak, Grzegorz Piskorz, Marcela Spišáková, Daniela Mačková
Format: Article
Language:English
Published: Warsaw University of Life Sciences 2018-04-01
Series:Przegląd Naukowy Inżynieria i Kształtowanie Środowiska
Subjects:
Online Access: http://iks.pn.sggw.pl/PN79/A7/art7.pdf
id doaj-9181286e4dbd4a2daf355431eb239e1e
record_format Article
spelling doaj-9181286e4dbd4a2daf355431eb239e1e2020-11-24T20:54:19ZengWarsaw University of Life SciencesPrzegląd Naukowy Inżynieria i Kształtowanie Środowiska1732-93532543-74962018-04-01271718110.22630/PNIKS.2018.27.1.7Causes of delays in construction works resulting from the provisions of the contract in Poland and SlovakiaAgnieszka Leśniak0Grzegorz Piskorz1Marcela Spišáková2Daniela Mačková3 Faculty of Civil Engineering, Cracow University of Technology PhD student of Cracow University of Technology Faculty of Civil Engineering, Technical University of Kosice Faculty of Civil Engineering, Technical University of Kosice Any construction project, even one that is excellently planned and organized, is prone to the risk of unforeseen events and problems, which in effect can cause late completion of works. The paper presents the results of the research conducted among Polish and Slovakian building contractors. One attempt was to identify and assess the potential causes of delays in the construction works resulting from the provisions of the contract. The knowledge of these factors can help contractors to take protective measures, reducing the risk of delays during the implementation of construction works. http://iks.pn.sggw.pl/PN79/A7/art7.pdf construction worksdelays factorscontractorsquestionnaire survey
collection DOAJ
language English
format Article
sources DOAJ
author Agnieszka Leśniak
Grzegorz Piskorz
Marcela Spišáková
Daniela Mačková
spellingShingle Agnieszka Leśniak
Grzegorz Piskorz
Marcela Spišáková
Daniela Mačková
Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia
Przegląd Naukowy Inżynieria i Kształtowanie Środowiska
construction works
delays factors
contractors
questionnaire survey
author_facet Agnieszka Leśniak
Grzegorz Piskorz
Marcela Spišáková
Daniela Mačková
author_sort Agnieszka Leśniak
title Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia
title_short Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia
title_full Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia
title_fullStr Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia
title_full_unstemmed Causes of delays in construction works resulting from the provisions of the contract in Poland and Slovakia
title_sort causes of delays in construction works resulting from the provisions of the contract in poland and slovakia
publisher Warsaw University of Life Sciences
series Przegląd Naukowy Inżynieria i Kształtowanie Środowiska
issn 1732-9353
2543-7496
publishDate 2018-04-01
description Any construction project, even one that is excellently planned and organized, is prone to the risk of unforeseen events and problems, which in effect can cause late completion of works. The paper presents the results of the research conducted among Polish and Slovakian building contractors. One attempt was to identify and assess the potential causes of delays in the construction works resulting from the provisions of the contract. The knowledge of these factors can help contractors to take protective measures, reducing the risk of delays during the implementation of construction works.
topic construction works
delays factors
contractors
questionnaire survey
url http://iks.pn.sggw.pl/PN79/A7/art7.pdf
work_keys_str_mv AT agnieszkalesniak causesofdelaysinconstructionworksresultingfromtheprovisionsofthecontractinpolandandslovakia
AT grzegorzpiskorz causesofdelaysinconstructionworksresultingfromtheprovisionsofthecontractinpolandandslovakia
AT marcelaspisakova causesofdelaysinconstructionworksresultingfromtheprovisionsofthecontractinpolandandslovakia
AT danielamackova causesofdelaysinconstructionworksresultingfromtheprovisionsofthecontractinpolandandslovakia
_version_ 1716794844051931136