Selection of alternative solutions in the optimization problem of network diagrams of project implementation

The object of research is a model network diagram of the project implementation in the form of a diagram, in which individual operations are represented by arcs, and vertices are considered as events corresponding to the beginning and end of operations. The term «model» is understood as an arbitrary...

Full description

Bibliographic Details
Main Author: Olena Domina
Format: Article
Language:English
Published: PC Technology Center 2020-08-01
Series:Technology Audit and Production Reserves
Subjects:
Online Access:http://journals.uran.ua/tarp/article/view/210848
id doaj-54f55484d084465eac19d88e3671ef9b
record_format Article
spelling doaj-54f55484d084465eac19d88e3671ef9b2020-11-25T03:42:10ZengPC Technology CenterTechnology Audit and Production Reserves2664-99692706-54482020-08-0144(54)92210.15587/2706-5448.2020.210848210848Selection of alternative solutions in the optimization problem of network diagrams of project implementationOlena Domina0Scientific Route OÜ Narva mnt 7-634, Tallinn, Estonia, 10117The object of research is a model network diagram of the project implementation in the form of a diagram, in which individual operations are represented by arcs, and vertices are considered as events corresponding to the beginning and end of operations. The term «model» is understood as an arbitrary network diagram, in relation to the parameters of which the solution is already known. One of the most problematic areas is the lack of substantiated methods of formalizing the task of optimizing network diagrams, allowing for a targeted selection of early start dates for individual operations within the project, ensuring optimal solutions for the selected criteria. In this study, such criteria are the possibility of shifting the operation with the maximum intensity in a given time interval, and the uniformity of the workload of personnel, assessed by the ratio of the maximum and minimum intensities y=qmax/qmin for the analyzed version of the network diagram. Methods of network planning and management, mathematical experimental planning and optimization methods are used. The results obtained confirm the possibility of using the proposed methods for solving optimization problems with respect to arbitrary network diagrams. This is due to the fact that the proposed methods for optimizing network diagrams allow one to obtain regression equations that serve as mathematical models for making targeted decisions on the choice of early start dates for operations that provide the best results in relation to the selected optimization criteria for network diagram. The features of the proposed solutions are: conditions for the selection of input variables, a procedure for the targeted selection of early start dates for operations with the highest load intensity of personnel, and providing optimal solutions for the criterion of minimizing uneven load. Thanks to these features, it is possible to optimize network diagrams with arbitrary source data. To do this, it is enough to apply the proposed procedure for your version of the network diagram, having previously estimated possible alternatives with respect to the choice of significantly influencing input variables and the intervals of their variation.http://journals.uran.ua/tarp/article/view/210848network diagramalternative solutionscentral compositional orthogonal designpeak load intensityuneven workload of personnel.
collection DOAJ
language English
format Article
sources DOAJ
author Olena Domina
spellingShingle Olena Domina
Selection of alternative solutions in the optimization problem of network diagrams of project implementation
Technology Audit and Production Reserves
network diagram
alternative solutions
central compositional orthogonal design
peak load intensity
uneven workload of personnel.
author_facet Olena Domina
author_sort Olena Domina
title Selection of alternative solutions in the optimization problem of network diagrams of project implementation
title_short Selection of alternative solutions in the optimization problem of network diagrams of project implementation
title_full Selection of alternative solutions in the optimization problem of network diagrams of project implementation
title_fullStr Selection of alternative solutions in the optimization problem of network diagrams of project implementation
title_full_unstemmed Selection of alternative solutions in the optimization problem of network diagrams of project implementation
title_sort selection of alternative solutions in the optimization problem of network diagrams of project implementation
publisher PC Technology Center
series Technology Audit and Production Reserves
issn 2664-9969
2706-5448
publishDate 2020-08-01
description The object of research is a model network diagram of the project implementation in the form of a diagram, in which individual operations are represented by arcs, and vertices are considered as events corresponding to the beginning and end of operations. The term «model» is understood as an arbitrary network diagram, in relation to the parameters of which the solution is already known. One of the most problematic areas is the lack of substantiated methods of formalizing the task of optimizing network diagrams, allowing for a targeted selection of early start dates for individual operations within the project, ensuring optimal solutions for the selected criteria. In this study, such criteria are the possibility of shifting the operation with the maximum intensity in a given time interval, and the uniformity of the workload of personnel, assessed by the ratio of the maximum and minimum intensities y=qmax/qmin for the analyzed version of the network diagram. Methods of network planning and management, mathematical experimental planning and optimization methods are used. The results obtained confirm the possibility of using the proposed methods for solving optimization problems with respect to arbitrary network diagrams. This is due to the fact that the proposed methods for optimizing network diagrams allow one to obtain regression equations that serve as mathematical models for making targeted decisions on the choice of early start dates for operations that provide the best results in relation to the selected optimization criteria for network diagram. The features of the proposed solutions are: conditions for the selection of input variables, a procedure for the targeted selection of early start dates for operations with the highest load intensity of personnel, and providing optimal solutions for the criterion of minimizing uneven load. Thanks to these features, it is possible to optimize network diagrams with arbitrary source data. To do this, it is enough to apply the proposed procedure for your version of the network diagram, having previously estimated possible alternatives with respect to the choice of significantly influencing input variables and the intervals of their variation.
topic network diagram
alternative solutions
central compositional orthogonal design
peak load intensity
uneven workload of personnel.