PROCESS TIME OPTIMIZATION IN DEPOSITOR AND FILLER
As in any industry, in soft drink manufacturing demand, customer service and production is of great importance that forces this production to have their equipment and production machines in optimal conditions for the product to be in the hands of the consumer without delays, therefore it is imp...
Main Authors: | , , , , |
---|---|
Format: | Article |
Language: | English |
Published: |
Universidad Autónoma Indígena de México
2017-07-01
|
Series: | Ra Ximhai |
Subjects: | |
Online Access: | https://drive.google.com/file/d/18BjEAJm9UtVYzH4RYzy9Jc7oAgEWvk_9/view |
Summary: | As in any industry, in soft drink manufacturing demand,
customer service and production is of great importance that
forces this production to have their equipment and
production machines in optimal conditions for the product
to be in the hands of the consumer without delays,
therefore it is important to have the established times of
each process, since the syrup is elaborated, packaged,
distributed, until it is purchased by the consumer.
After a chronometer analysis, the most common faults were
detected in each analyzed process. In the filler machine the
most frequent faults are: accumulation of bottles in the
subsequent and previous processes to filling process, which
in general the cause of the collection of bottles is due to
failures in the other equipment of the production line. In the
process of unloading the most common faults are: boxes
jammed in bump and pusher (pushing boxes); boxes fallen
in rollers and platforms transporter. According to
observations in each machine, the actions to be followed
are presented to solve the problems that arise.
Also described the methodology to obtain results, to data
analyze and decisions. Firstly an analysis of operations is
done to know each machine, supported by the manuals of the machines and the operators themselves a study of times
is done by chronometer to determine the standard time of
the process where also they present the most common
faults, then observations are made on the machines
according to the determined sample size, thus obtaining the
information necessary to take measurements and to make
the study of optimization of the production processes. An
analysis of the predetermined process times is also
performed by the MTM methods and the MOST time
analysis.
The results of operators with MTM:
Fault Filler = 0.846 minutes, Faultless Filler = 0.61 minutes,
Fault Breaker = 0.74 minutes and Fault Flasher = 0.45
minutes.
The results of MOST operators are:
Fault Filler = 2.58 minutes, Filler Fails = 2.35 minutes, Failure
Breaker = 2.15 minutes, Failure Breaker = 1.68 minutes.
It concludes that the time analysis is an adequate tool to
determine the time of the processes and to make
recommendations of the improvement, to minimize the lost
time and to optimize the conditions of the operation in the
process. |
---|---|